Loring Greenway Association
Loring Greenway Association
  • Home
  • About Us
    • History
    • Board Meeting Minutes
  • Volunteer
  • Give
    • Give
    • Give for Healthy Trees
    • Annual Reports
  • News
    • Articles
    • Playground
    • Playground Build: Week 1
    • Playground Build: Week 2
    • Newsletters
  • Contact Us
  • More
    • Home
    • About Us
      • History
      • Board Meeting Minutes
    • Volunteer
    • Give
      • Give
      • Give for Healthy Trees
      • Annual Reports
    • News
      • Articles
      • Playground
      • Playground Build: Week 1
      • Playground Build: Week 2
      • Newsletters
    • Contact Us
  • Home
  • About Us
    • History
    • Board Meeting Minutes
  • Volunteer
  • Give
    • Give
    • Give for Healthy Trees
    • Annual Reports
  • News
    • Articles
    • Playground
    • Playground Build: Week 1
    • Playground Build: Week 2
    • Newsletters
  • Contact Us

Playground Construction: Week One

Setting Site Perimeters

City of Minneapolis contractor family-owned Albrecht Company, a Roseville landscaper, started playground construction on September 30. A  team from subcontractor National Fencing cordoned off the job site.

Relay for Reuse

From bobcat to compact excavator, to wheel loader to dump truck, sand was delivered to a recycling center.  This relay was repeated about 20 times during the week to to remove excess sand from the playground.

First Playground Equipment Added

Spinning and springer equipment installed on Thursday are signs of fun ahead! 